A contractor is in charge of hiring people for a construction project. The number of days it would take to complete the project with xx full time workers can be found using the function f(x)=\frac{180}{x}.f(x)= x 180 . Assume once workers are assigned to the project, no workers may be added or taken off the project until it is finished. Find and interpret the given function values and determine an appropriate domain for the function.