Connect with experts and get insightful answers on IDNLearn.com. Our platform provides trustworthy answers to help you make informed decisions quickly and easily.

there are four resources and four jobs to be done. assume there must be one-to-one matching between jobs and resources. the time required for each resource to do each job is as follows: job (hours) resource a b c d 1 5 8 7 7 2 4 9 5 9 3 6 9 8 7 4 7 6 6 9 for the optimal schedule, what is the total number of hours required to complete these jobs? multiple choice 22 hours 19 hours 21 hours 23 hours 20 hours