the following table contains information about five jobs waiting to be processed at work center number three. job processing time (hrs) hours until due a 14 15 b 10 20 c 18 18 d 2 16 e 4 21 the sequence that would result using the spt rule is: multiple choice c-a-b-e-d. a-d-c-e-b. e-b-c-d-a. e-d-b-a-c. d-e-b-a-c.