A company needs to make 10,000 copies of a flyer to advertise a special offer. The company
has two printers to do the job. One printer could complete all the flyers in 3 hours. Using both
printers, all the flyers could be completed in 1 hour and 40 minutes. How long would it take the other printer alone to complete all the flyers?