Get the information you need from a community of experts on IDNLearn.com. Join our knowledgeable community and access a wealth of reliable answers to your most pressing questions.
In a batch machining operation, setup time is 1.5 hr and batch size is 80 units. The cycle
time consists of part handling time of 30 sec and processing time of 1.37 min. One part
is produced each cycle. Tool changes must be performed every 10 parts and this takes
2.0 min. Determine (a) average cycle time, (b) time to complete the batch, and (c) average
production rate.
Sagot :
Your presence in our community is highly appreciated. Keep sharing your insights and solutions. Together, we can build a rich and valuable knowledge resource for everyone. IDNLearn.com is your go-to source for accurate answers. Thanks for stopping by, and come back for more helpful information.