IDNLearn.com is the place where your questions are met with thoughtful and precise answers. Discover trustworthy solutions to your questions quickly and accurately with help from our dedicated community of experts.
Now suppose that there is an option to abandon the project after 1 year! so the project costs $137,000 to begin today. This begins phase 1 there is learning involved in the first year. Proceed to phase 2 only if phase 1 is promising. There is a 10% chance that phase 1 will be promising. If phase 1 is promising invest $2. 75 million next year and build the plant. It will generate $350,000 per year forever (starting the year after) and is almost risk free. If phase 1 is not promising abandon the project. What is the npv of the project? company wacc
Sagot :
We are delighted to have you as part of our community. Keep asking, answering, and sharing your insights. Together, we can create a valuable knowledge resource. Discover the answers you need at IDNLearn.com. Thank you for visiting, and we hope to see you again for more solutions.