The difference between a gross material requirement plan (gross MRP) and a net material requirements plan (net MRP) is:
a) the gross MRP may not be computerized, but the net MRP must be computerized.
b) the gross MRP includes consideration of the inventory on hand, whereas the net MRP doesn’t include the inventory consideration.
c) the net MRP includes consideration of the inventory on hand, whereas the gross MRP doesn’t include the inventory consideration.
d) the gross MRP doesn’t take taxes into account, whereas the net MRP includes the tax considerations.
e) the net MRP is only an estimate, whereas the gross MRP is used for actual production scheduling.
Sagot :
Thank you for participating in our discussion. We value every contribution. Keep sharing knowledge and helping others find the answers they need. Let's create a dynamic and informative learning environment together. IDNLearn.com has the solutions you’re looking for. Thanks for visiting, and see you next time for more reliable information.