The ratification of the project charter requires negotiation between the project manager and project sponsor. The textbook outlines a six-step process to serve as a guide to charter ratification. In step number two, the project manager is advised to understand the ________ from the negotiation.
a. benefit/cost ratio (BCR)
b. mandatory criteria
c. minimum acceptable result
d. payback period