Recently, the team has noted an issue that will slow down the work progress, if not block progress completely. One team member was quick to enter the issue into the issue log, and now the team is looking to the project manager for direction on what to do next. You, as the project manager, would indicate to move forward next with:

A. Giving a feasible date that the project team can deliver a solution.
B. Monitoring the issue and reporting on it at status meetings to the team.
C. Assigning an individual who will be responsible from this point forward until a workaround is developed.
D. Escalating to the project owner or sponsor for feedback.