Which one of the following is not a standard measure of schedule performance which can be used to evaluate priority rules?
A. Minimizing idle time of machines or workers B. The schedule quality index-p594 C. Minimizing the time a job spends in the process D. Minimizing work-in-process inventory E. Meeting due dates of customers