IDNLearn.com provides a collaborative environment for finding and sharing answers. Get the information you need from our community of experts who provide accurate and comprehensive answers to all your questions.

Max and Jane need to push a heavy sled 5 miles. Together they can push the sled one mile for every hour of work, but alone neither one of them can move the sled. Every hour starting at 9 a.m., Max rolls a standard six-sided die. If he rolls anything other than a six, he goes to work pushing the sled. If Max rolls a four or more, Jane rolls the die. If Jane rolls the die and rolls a four or less, she goes to work pushing the sled. Otherwise, she just takes a break. If they follow this procedure continually until the job is done, what time do you expect they will finish the job?