Expand your horizons with the diverse and informative answers found on IDNLearn.com. Get the information you need from our community of experts who provide accurate and comprehensive answers to all your questions.

A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,100 units and was completed in 20,300 hours at a total labor cost of $198,000. What is the direct labor rate variance?