In the agile project management approach: a. Monitoring risks is likely to be performed within an iteration/sprint. b. Monitoring risks happens immediately after an iteration/sprint ends. c. Monitoring risks could result in changes to the product backlog. d. Monitoring risks is done during the iteration/sprint daily standup.