IDNLearn.com makes it easy to find answers and share knowledge with others. Discover reliable answers to your questions with our extensive database of expert knowledge.

how do you find the mean completion time of a PERT network diagram?​

Sagot :

Answer:

PERT is an estimating technique that uses a weighted average of three numbers (see below) to come up with a final estimate. The resulting PERT estimate is calculated as (O + 4M + P)/6. This is called a "weighted average" since the most likely estimate is weighted four times as much as the other two values.