Using the information below for Laurels Company; determine the manufacturing costs added during the current year:

Direct materials used $5,000
Direct labor 7,000
Total factory overhead 5,100
Beginning work in process 3,000
Ending work in process 4,000

a. $12,000.
b. $16,100.
c. $17,100.
d. $18,100.
e. $13,600.


Sagot :

Answer:

C. $17,100

Explanation:

The manufacturing cost for the year is computed as;

Manufacturing cost = (Direct materials + Direct labor + Total factory overheads) + Beginning work in process - Ending work in process

Direct materials

$5,000

Direct labor

$7,000

Total factory overheads.

$5,100

Direct manufacturing costs

$17,100

Add beginning work in process

$3,000

Less ending work in process

($4,000)

Total manufacturing costs

$16,100