Watson's Computer Company expects to produce 2,250 computers. Watson's Computer Company also expects to use 13,000 parts and have 20 setups.The allocation rate for materials handling will be

Sagot :

Answer:

$4.00

Explanation:

Calculation for what The allocation rate for materials handling will be

Using this formula

Materials handling allocation rate=Material Handling/Expected parts to use

Let plug in the formula

Materials handling allocation rate=$52,000/13,000 parts

Materials handling allocation rate=$4.00

Therefore The allocation rate for materials handling will be $4.00