Answer:
a. Materials, 100%; labor, 100%; overhead cost, 40%.
Explanation:
The work in Process have already passed the mark at which Materials and Labor are added, that is the start of its production process so these are both 100% complete. Overheads are 40 % complete, which is the extent of work done on them since they occur evenly.