Answer:
c. $6,500.
Explanation:
The computation of the material cost assigned to Job 971 is as follows:
= Budgeted Overhead × Material Weight for Job 971 ÷ Total Weight
= $160,000 × 130 ÷ 3200
=$6,500
Hence, the material cost assigned to Job 971 is $6,500