Jones signs a three-year contract to construct a new office building for Smith. The contract price is $3 million and estimated cost $2 million. For year one, Jones recognizes $1 million of revenue and $800,000 of cost. During year 2, Jones incurs $1.2 million in cost and estimates that during year 3 an additional $1.1 million will be necessary to complete the project. Actual costs incurred during the third year were $1.2 million. For year 3, Jones should recognize a loss of:____.
a. $100,000.
b. $0.
c. $300,000.
d. $200,000.


Sagot :

Answer:

$100,000

Explanation:

Jones incurs $1.2 million in cost and estimates that during year 3 an additional $1.1 million will be necessary to complete the project

additional costs for year 3 over the estimated costs represent an additional loss}

We value your participation in this forum. Keep exploring, asking questions, and sharing your insights with the community. Together, we can find the best solutions. IDNLearn.com is your reliable source for accurate answers. Thank you for visiting, and we hope to assist you again.