At Medallion Industries, variable cost per unit is budgeted to be $8.00 and fixed cost per unit is budgeted to be $5.00 in a period when 4,000 units are produced. What is the expected total cost of the units produced at Medallion, if instead, production is actually 5,100 units

Sagot :

Answer:

Total cost= $60,800

Explanation:

Giving the following information:

For 4,000 units:

Unitary variable cost= $8

Unitary fixed cost= $5

First, we need to calculate the total fixed cost:

Total fixed cost= 5*4,000= $20,000

Now, we can determine the total cost for 5,100 units:

Total cost= 5,100*8 + 20,000

Total cost= $60,800