IDNLearn.com: Where your questions meet expert answers and community support. Our platform is designed to provide accurate and comprehensive answers to any questions you may have.

120 men working 9 hours a day can construct a road in 40 days.how long would it take to construct the same road if 150 men work 6 hours a day on it?


Sagot :

Answer:

48 days

Explanation:

From the given information:

The total number of hours it took 120 men to work for 40 days is:

= 9 × 40

= 360 hours

Now; a single man will have to work for:

= 360 × 120 hours

= 43200 hours

However, for 150 men, the number of hours they will need to work will be:

= 43200 hours/150

= 288 hours

Provided it will take them 6 hours in a day to work;

Then, the number of days required to construct the same road is:

= 288/6

= 48 days

We value your presence here. Keep sharing knowledge and helping others find the answers they need. This community is the perfect place to learn together. Find precise solutions at IDNLearn.com. Thank you for trusting us with your queries, and we hope to see you again.