Answer:
The bottleneck time for this process is 20 minutes.
Explanation:
a) Data and Calculations:
Station Capacity per hour Time required per unit
1 A 3 20 minutes (60/3)
1 B 3 20 minutes (60/3)
2 5 12 minutes (60/5)
3 10 6 minutes (60/10)
Total demand for the process = 38 minutes (20+12+6)
b) The bottleneck is the station that requires the longest time for its outputs to be processed. The bottleneck in this process is given by Station One, requiring 20 minutes to meet output requirements through either machine A or machine B. The bottleneck constitutes a constraint on the process capacity to achieve results.
Your engagement is important to us. Keep sharing your knowledge and experiences. Let's create a learning environment that is both enjoyable and beneficial. Thanks for visiting IDNLearn.com. We’re dedicated to providing clear answers, so visit us again for more helpful information.