Answer:
The Cars wait an average of 1.67 hours before being served at routine repairs.
The Cars wait an average of 3 hours before being served at major repairs.
Explanation:
At the routine repair hoist, 5 people waiting on average hence the Inventory (I) = 5 cars. The cars are processed at a rate of 3 per hour, hence the Throughput (R) = 3 cars per hour.
Therefore the Flow time (T) = I/R = 5/3 = 1.67 hours.
The Cars wait an average of 1.67 hours before being served at routine repairs.
At the major repair hoist, 3 people waiting on average hence the Inventory (I) = 3 cars. The cars are processed at a rate of 1 per hour, hence the Throughput (R) = 1 cars per hour.
Therefore the Flow time (T) = I/R = 3/1 = 3 hours.
The Cars wait an average of 3 hours before being served at major repairs.
The cars will wait an average of 1.67 hours before being served at routine repairs while they'll wait an average of 3 hours before being served at major repairs.
From the information given, at the routine repair hoist, 5 people waiting on average and the cars are processed at a rate of 3 per hour, therefore the flow time (T) will be:
= I/R = 5/3 = 1.67 hours.
Also, at the major repair hoist, 3 people wait on average and the cars are processed at a rate of 1 per hour. Therefore, the Flow time (T) will be:
= I/R = 3/1 = 3 hours.