IDNLearn.com makes it easy to find accurate answers to your questions. Join our interactive Q&A community and get reliable, detailed answers from experienced professionals across a variety of topics.

Trek Company has the following production data for April: units transferred out 40,200, and ending work in process 6,220 units that are 100% complete for materials and 40% complete for conversion costs. If unit materials cost is $4 and unit conversion cost is $10. Determine the costs to be assigned to the units transferred out and the units in ending work in process.

Sagot :

Answer:

the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively

Explanation:

The computation is shown below:

Cost assign to units transferred out is

= 40,200 units × $4 + 40,200  units ×  $10

= $160,800 + $402,000

= $562,800

And, the Cost assign to work in progress is

= 6,220  units × $4 + (6,220 units × 0.40) × $10

= $24,880 + $24,880

= $49,760

Hence, the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively

Thank you for participating in our discussion. We value every contribution. Keep sharing knowledge and helping others find the answers they need. Let's create a dynamic and informative learning environment together. Thank you for visiting IDNLearn.com. We’re here to provide accurate and reliable answers, so visit us again soon.