Why is it necessary to track the progress of a plan?
O A. To create a progress chart for employees to help them calculate
their pay
O B. To ensure the plan is based on faulty assumptions
O C. To identify potential problems that could impact the schedule
O D. To provide information for manager's reports


Sagot :

Answer:

to identify potential problems that could impact the schedule

Explanation:

a p e x

It is important for an organization to track the process of a plan in order to identify potential problems that could impact the schedule. Hence, option C holds true.

What is planning?

Planning is the most basic function of management of a business organization. It is a continuous process. Planning involves setting up the goals and objectives and the actions needed to achieve them.

Furthermore, because planning is a continuous process, it helps in identification of difficulties that may create obstacles in achievement of organizational goals.

Hence, option C holds true regarding planning.

Learn more about planning here:

https://brainly.com/question/22590420