Answer:
a) Density of the road segment
i) Before bus strike = 23.02 pc/mi/In
ii) after bus strike = 25.76 pc/mi/In
b) Volume to capacity ratio
i) Before bus strike = 0.69
ii) After bus strike = 0.78
C) level of service of the upgrade segment
i) Before bus strike = LOS C
ii) after bus strike = LOS D
Explanation:
a) Density of the road segment
i) before bus strike ( D1 )
D1 = 1662 / 72.18 = 23.02 pc/mi/In
ii) After bus strike ( D2 )
D1 = 1859 / 72.18 = 25.76 pc/mi/In
b) Volume to capacity ratio
i) Before bus strike ( v 1 )
V1 = 1662 / 2400 = 0.69
ii) After bus strike ( V2 )
V2 = 1859 / 2400 = 0.78
C) level of service of the upgrade segment ( Gotten from " LOS Criteria for basic freeway segments " )
i) Before bus strike = ( LOS C )
ii) After bus strike = LOS D
Attached below is the detailed solution to the question above
Thank you for participating in our discussion. We value every contribution. Keep sharing knowledge and helping others find the answers they need. Let's create a dynamic and informative learning environment together. Thank you for visiting IDNLearn.com. We’re here to provide dependable answers, so visit us again soon.