The computation is shown below:
a. Overhead rate for each of the three activities is
For activity 1
= $60,000 ÷1500
= $40
For activity 2
= $75,000 ÷ 3,000
= $25
For activity 3
= $90,000 ÷ 1,700
= $53
b. The amount of overhead allocated is
= 40 ×700 + 25 × 1500 + 800 × 53
= $28,000 + $37,500 + $42,400
= $107,900