Get the information you need from a community of experts on IDNLearn.com. Discover reliable answers to your questions with our extensive database of expert knowledge.

Louis agreed to provide all the apples that Cindy's Cider Mill will need at $3 per bushel unless weather conditions require additional labor to be hired. The contract further provides that in the case of bad weather requiring additional workers the rate would be $3.50 per bushel. As a result of an early freeze warning, Louis learns he will have to hire 100 additional workers and will lose thousands of dollars even at the $3.50 per bushel rate. Louis now wants to get out of his contract. Can he

Sagot :

Answer: No, the parties expected the hardship and provided for it in their contract

Explanation:

Based on the information given in the question, Louis cannot get out of the contract. This is because the parties expected the hardship and provided for it in their contract.

This can be deduced when rather than paying $3 per bushel, in case of bad weather requiring additional workers, the rate would be $3.50 per bushel and it was agreed.

Therefore, Louis can't get out of the contract.

Your participation means a lot to us. Keep sharing information and solutions. This community grows thanks to the amazing contributions from members like you. Thanks for visiting IDNLearn.com. We’re dedicated to providing clear answers, so visit us again for more helpful information.