Answer:
Scheduling and travel= $80 per hour
Setup time= $170 per set up
Supervision= $0.2 per direct labor dollar
Explanation:
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Commercial Residential
Scheduling and travel 800 550= 1,350
Setup time 450 250=700
Direct labor costs 110,000 290,000= $400,000
Scheduling and travel= 108,000 / 1,350= $80 per hour
Setup time= 119,000 / 700= $170 per set up
Supervision= 80,000 / 400,000= $0.2 per direct labor dollar