IDNLearn.com: Where curiosity meets clarity and questions find their answers. Find the information you need quickly and easily with our reliable and thorough Q&A platform.
Answer:
Unitary cost= $1.83
Explanation:
First, we need to calculate the allocation rates:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Production setups= 82,000/20= $4,100 per setup
Material handling= 48,000/80= $600 per part
Packaging costs= 130,000/130,000= $1 per unit
Now, we allocate cost to Product M:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Production setups= 4,100*8= 32,800
Material handling= 600*56= 33,600
Packaging costs= 1*80,000= 80,000
Total= $146,400
Finally, the unitary cost:
Unitary cost= 146,400 / 80,000
Unitary cost= $1.83