IDNLearn.com provides a collaborative platform for sharing and gaining knowledge. Get accurate and comprehensive answers from our network of experienced professionals.
Sagot :
Answer: See explanation
Explanation:
1. Compute the price (rate) per hour of direct labor.
This will be:
= [45 + (185,300 / 10,900)]× 1.33
= (45 + 17) × 1.33
= 62 × 1.33
= $82.46
2. Compute the materials markup.
This will be:
= =(355,300 / 2090,000) + 33%
= 0.17 + 33%
= 17% + 33%
= 50%
3. What price should the company quote for a job requiring five labor hours and $670 in parts?
This will be:
= (670 × 1.5) + (82.46 × 5)
= 1005 + 412.3
= $1417.30