Join IDNLearn.com today and start getting the answers you've been searching for. Get accurate and detailed answers to your questions from our knowledgeable and dedicated community members.

It takes 14 hours to seal a hardwood floor with varnish. If each coat requires 3

1/4 hours to dry,


how many coats are applied?


Sagot :

Answer:

4.3 coats

Step-by-step explanation:

if 1 coat takes 3 1/4 hours (same as 3.25 hours)

3.25 hours = 1 coat

14 hours = x coats

(cross multiply)

3.25 × x = 14 × 1

3.25x = 14

(divide both sides by 3.25)

x = 4.3

therefore, 4.3 coats are applied