Join the IDNLearn.com community and start getting the answers you need today. Get the information you need from our community of experts who provide accurate and thorough answers to all your questions.

Math , pleaaaase

You are given the results of measurements of sizes of a crushed stone for road
construction. The technical requirement is the following: The mean size of the stones must be in the interval [33-36] mm and standard deviation must be smaller than 6 mm. Will this batch pass the technical control?


Math Pleaaaase You Are Given The Results Of Measurements Of Sizes Of A Crushed Stone For Road Construction The Technical Requirement Is The Following The Mean S class=

Sagot :

Answer:

The standard deviation is above 6 mm, which means that this batch does not pass the technical control.

Step-by-step explanation:

Mean of the batch:

The mean of the batch is the sum of all values divided by the number of items. So

[tex]M = \frac{31+32+38+34+45+41+24}{7} = 35[/tex]

Mean in the desired interval.

Standard deviation:

Square root of the sum of the difference squared between each term and the mean, divided by the number of itens. So

[tex]S = \sqrt{\frac{(31-35)^2+(32-35)^2+(38-35)^2+(34-35)^2+(45-35)^2+(41-35)^2+(24-35)^2}{7}} = 6.46[/tex]

The standard deviation is above 6 mm, which means that this batch does not pass the technical control.