Answer:
Variance (Unfavorable) (NZD 340,000)
Explanation:
Budget Variance using exchange rate projected at the time of budget
Budget Actual Variance Exc. Rate Variance in NZD
MYR MYR
Revenue 12000000 11000000 -1000000 0.34 -340000
Expenses 9000000 9000000 0 0.34 0
Profit 3000000 2000000 -1000000 0.34 -340000