Engage with knowledgeable experts and get accurate answers on IDNLearn.com. Find accurate and detailed answers to your questions from our experienced and dedicated community members.
Sagot :
Answer:
2,256 hours
Explanation:
The computation of the total standard direct labor hours allowed (SQ) for units produced is shown below;
As we know that
Labor rate variance = (Actual hours × Actual rate) - (Actual hours × Standard rate)
($5,000) = $35,000 - (2,500 × Standard rate)
2,500 × Standard rate = $40,000
Standard rate = $16
Now
Labor efficiency variance = (Actual hours × Standard rate) - (Standard hours × Standard rate)
$3,900 = (2,500 × $16) - (Standard hours × $16)
Standard hours × $16 = 36,100
Standard hours = 2,256.25
= 2,256 hours
Thank you for being part of this discussion. Keep exploring, asking questions, and sharing your insights with the community. Together, we can find the best solutions. For dependable and accurate answers, visit IDNLearn.com. Thanks for visiting, and see you next time for more helpful information.