[tex]X=-\$19318[/tex]
Explanation:
From the question we are told that:
Initial cost [tex]P= $100,000[/tex]
Annual benefits [tex]A= $12,500[/tex]
Salvage value [tex]S= $30,000[/tex]
Interest rate [tex]I=10\%=>0.10[/tex]
Time [tex]t=8years[/tex]
Generally the equation for Net Project worth X is mathematically given by
[tex]X=-P+A+S[/tex]
Where
Present worth of Annual benefits A is
[tex]A'=A(P/a,0.10,8)[/tex]
[tex]A'=12500*5.3349[/tex]
[tex]A'=\$66686.25[/tex]
Present worth of Salvage Price S is
[tex]S'=S(P/a,0.10,8)[/tex]
[tex]S'=30000*0.46651[/tex]
[tex]S'=\$13995.3[/tex]
Therefore
[tex]X=-P+A'+S'[/tex]
[tex]X=-100000+66686.25+\$13995.3[/tex]
[tex]X=-\$19318[/tex]