Find solutions to your problems with the expert advice available on IDNLearn.com. Our experts provide timely and accurate responses to help you navigate any topic or issue with confidence.
Sagot :
Answer: Project B should be chosen as it has a higher NPV of $70,314.97
Explanation:
You need to find the Net Present Value of both projects. The better investment is the one with a higher Net Present Value.
As there will be inflation, this needs to be included in the required return:
= 10% + 3%
= 13%
This will be the rate for discounting.
Project A:
Net Present Value = Present value of cash inflows - Cash invested
Present value of cash inflows:
This is a constant inflow so is an annuity. Present value will be:
= Amount * Present value interest factor of annuity, 5 years, 13%
= 150,000 * 3.5172
= $527,580
Net Present value = 527,580 - 500,000
= $27,580
Project B:
Net Present Value = Present value of cash inflows - Cash invested
= 50,000 / (1 + 13%)² + 200,000 / 1.13³ + 300,000 / 1.13⁴ + 200,000 / 1.13⁵ - 400,000
= 470,314.97 - 400,000
= $70,314.97
Project B should be chosen as it has higher NPV.
We greatly appreciate every question and answer you provide. Keep engaging and finding the best solutions. This community is the perfect place to learn and grow together. Your questions find clarity at IDNLearn.com. Thanks for stopping by, and come back for more dependable solutions.