Answer:
$102.3 per machine hour
Explanation:
We can compute the total production engineering cost per hour by using the following equation;
Cost per machine hour = (Fixed cost + Variable cost) / Total machine hours
But first, we need to calculate variable cost at 9,600 hours;
= $766,320 × 9,600hr / 9,300hr
= $791,040
Now, cost per machine hour
= $191,040 + $791,040 / 9,600hr
= $982,040 / 9,600hr
= $102.3 per machine hour