Predetermined manufacturing overhead rate= $97 per machine hour
Explanation:
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (6,920,000 + 840,000) / 80,000
Predetermined manufacturing overhead rate= $97 per machine hour