IDNLearn.com connects you with experts who provide accurate and reliable answers. Our Q&A platform offers detailed and trustworthy answers to ensure you have the information you need.
Sagot :
Answer:
Overhead per unit of Blinks= $43.65
Explanation:
Giving the following information:
Product Number of Units Labor Hours Per Unit
Blinks 964 3
Dinks 1,943 5
First, we need to calculate the total estimated overhead and the total number of labor hours:
Total estimated overhead= 103,800 + 79,600= $183,400
Total number of labor hours= (964*3) + (1,943*5)= 12,607
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 183,400 / 12,607
Predetermined manufacturing overhead rate= $14.55 per direct labor hour
Finally, we can allocate overhead to Blinks:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Blinks= 14.55*3= $43.65