If 40 men working on a U.S. government project can complete the job in 100 hours, how many men would be required to complete the job in 80 hours?

Sagot :

Answer:50

Step-by-step explanation:(40x100):80

Answer: 50 workers

Let the ratio be

(40×100):80

= 400/80

= 50

Therefore 50 workers will complete the same work in 80 hours.