15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Sagot :

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.