Answer:
Step-by-step explanation:
= 1/3 + 1/6 + 1/12 (LCM 12)
= 4/12 + 2/6 + 1/12
= 6/12
= 1/2
Therefore 1/2 = 2 days
They will all work together and finish the job in 2 days