1 by 6 of a construction work is finished in the first year, 1 by 8 part in the second year and 1 by 12 in the third year how much work is finished in 3 year

Sagot :

Answer:

3/8

Step-by-step explanation:

first year's work is 1/6

second year's work is 1/8

third year's work is 1/12

combining all 3 gives us

1/6 + 1/8 + 1/12

which simplifies to 3/8