Join the growing community of curious minds on IDNLearn.com and get the answers you need. Join our interactive Q&A community and get reliable, detailed answers from experienced professionals across a variety of topics.
Sagot :
Percentage and ratio word problems require understanding of the relationship between variables from which the question is formed
The options that give the correct values of the duration of the work are;
- [tex]41. \ c) \ \dfrac{4}{x}[/tex]
- [tex]42. \ d) \ \dfrac{4}{x} + \dfrac{6}{y} = \dfrac{1}{5}[/tex]
- 43. a) 35 days
- 44. c) 21·a + 28·b = 1
- 45. c) (42, 56)
Reasons:
41. Number of days it takes a man to complete the work alone = x days
Therefore;
[tex]The \ work \ done \ by \ the \ man \ in \ one \ day = \dfrac{1}{x}[/tex]
[tex]The \ work \ done \ in \ four \ days \ by\ the \ man = 4 \times \dfrac{1}{x} = \dfrac{4}{x}[/tex]
The correct option is [tex]c) \ \dfrac{4}{x}[/tex]
42. Number of days it takes a man to complete the work alone = x days
[tex]Work \ done \ by \ a\ man \ in \ one \ day = \dfrac{1}{x}[/tex]
[tex]Work \ done \ by \ four \ men \ in \ one \ day = \dfrac{4}{x}[/tex]
Number of days it takes a boy to complete the work alone = y days
[tex]Work \ done \ by \ a \ boy \ in \ one \ day = \dfrac{1}{x}[/tex]
[tex]Work \ done \ by \ six \ boys \ in \ one \ day = \dfrac{6}{y}[/tex]
4 men and 6 boys work for 5 days to complete the work
Therefore, work done by 4 men and 6 boys in 1 day is therefore;
[tex]\dfrac{4}{x} + \dfrac{6}{y} = \dfrac{1}{5}[/tex]
The correct option is therefore;
[tex]d) \ \dfrac{4}{x} + \dfrac{6}{y} = \dfrac{1}{5}[/tex]
43. As per the case study, we have;
Case 1
[tex]\dfrac{4}{x} + \dfrac{6}{y} = \dfrac{1}{5}[/tex]
Which gives;
[tex]\dfrac{6\cdot x + 4\cdot y}{y \cdot x} = \dfrac{1}{5}[/tex]
30·x + 20·y = y·x
Case 2
[tex]\dfrac{3}{x} + \dfrac{4}{y} = \dfrac{1}{7}[/tex]
Which gives;
[tex]\dfrac{4\cdot x + 3\cdot y}{y \cdot x} = \dfrac{1}{7}[/tex]
28·x + 21·y = y·x
Therefore;
30·x + 20·y = 28·x + 21·y
∴ 2·x = y
Plugging in the value of y = 2·x, in Case 1 gives;
[tex]\dfrac{4}{x} + \dfrac{6}{2 \cdot x} = \dfrac{1}{5}[/tex]
[tex]\dfrac{2 \times 4 + 6}{2 \times x} = \dfrac{14}{2 \times x} =\dfrac{7}{x} = \dfrac{1}{5}[/tex]
7 × 5 = x
x = 7 × 5 = 35
The number of days, x, it takes a man to complete the work alone, is given by option; a) 35 days
44. For the equation [tex]\dfrac{3}{x} + \dfrac{4}{y} = \dfrac{1}{7}[/tex], if [tex]a = \dfrac{1}{x}[/tex], and [tex]b = \dfrac{1}{y}[/tex], we have;
[tex]3 \cdot a+ 4\cdot y = \dfrac{1}{7}[/tex]
21·a + 28·y = 1
The correct option is option C. 21·a + 28·b = 1
45. A solution to the equation [tex]\dfrac{3}{x} + \dfrac{4}{y} = \dfrac{1}{7}[/tex], is given by the values of x, and y, that gives;
[tex]\dfrac{1}{14} + \dfrac{1}{14} = \dfrac{1}{7}[/tex]
We have;
3 × 14 = 42
4 × 14 = 56
Therefore, a solution to the equation is (42, 56)
The correct option is [tex]c) \ \underline{ (42, \ 56)}[/tex]
Learn more here:
https://brainly.com/question/11825953
https://brainly.com/question/14626596
https://brainly.com/question/15573651
Your participation means a lot to us. Keep sharing information and solutions. This community grows thanks to the amazing contributions from members like you. Thank you for trusting IDNLearn.com. We’re dedicated to providing accurate answers, so visit us again for more solutions.