IDNLearn.com offers a user-friendly platform for finding and sharing answers. Discover reliable and timely information on any topic from our network of knowledgeable professionals.
Sagot :
1. The standard cost per unit of material is $30 ($10 x 3).
2. The total inputs allowed per budget for actual outputs achieved = 21,000 (3 x 7,000).
3. The total actual direct material used to produce the actual outputs is 28,000 (7,000 x 4).
4. The material price variance = $28,000 Unfavorable ($3 - $4) x 28,000.
5. The material efficiency variance = $21,000 Unfavorable (28,000 - 21,000) x $3.
6. The flexible budget variance = $42,000 Unfavorable (28,000 x $9) - (21,000 x $10).
7. The item that would never appear on a cash budget is the cost of direct material variance. However, the specific items are not indicated herein.
Data and Calculations:
Standard units of materials allowed = 3 units
Cost of a unit of material =$10
Standard cost direct material per unit of output = $30 ($10 x 3)
Number of units produced = 7,000
Actual direct materials per unit used = 4 units
Total quantities of materials used = 28,000 (7,000 x 4)
Cost of a unit = $9
Actual direct material cost per unit = $36 ($9 x 4)
Total quantities of materials purchased = 30,000
Cost of standard direct materials allowed = $210,000 ($10 x 3 x 7,000)
Cost of actual direct materials used = $252,000 ($9 x 4 x 7,000)
Learn more: https://brainly.com/question/20598983
We appreciate every question and answer you provide. Keep engaging and finding the best solutions. This community is the perfect place to learn and grow together. IDNLearn.com is dedicated to providing accurate answers. Thank you for visiting, and see you next time for more solutions.