Moss Manufacturing makes products to customer specifications. Moss recently completed an order for 250 products and incurred costs of $4,200 on direct materials, $2,800 on direct labor, and $1,100 on manufacturing overhead for the products. If Moss uses job order costing, what is the cost per unit for this order

Sagot :

If Moss Manufacturing records costs based on a job order costing basis, the cost per unit will be $32.40

What is the cost per unit?

This can be found by the formula:

= (Direct materials + Direct labor + Overhead ) / Number of units produced

Solving gives:

= (4,200 + 2,800 + 1,100) 250

= 8,100 / 250

= $32.40

In conclusion, this would be $32.40.