Based on the given costs, the total cost of direct materials in June was $69,000.
Job 5 was completed in June and some of its material costs would be in June.
Job 5 June Material cost
= Total cost - May cost
= 15,000 - 6,000
= $9,000
Total material cost in June
= Job 5 cost + Job 6 cost + Job 7 cost
= 9,000 + 33,000 + 27,000
= $69,000
In conclusion, direct materials cost would be $69,000 in June.