When you link two tasks using the Link Tasks feature on the Task tab, Microsoft Project creates a _____ link.

Sagot :

A finish-to-start link is created by Microsoft Project when you link two tasks using the Link Tasks feature on the Task tab.

What is Microsoft Project?

Microsoft Project can be defined as a project management software product that is designed an developed by Microsoft Inc., so as to assist project managers in achieving the following project tasks:

  • Developing a schedule.
  • Analyzing workloads.
  • Assigning resources to tasks.
  • Tracking project progress.
  • Managing their project budget.

On Microsoft Project, a finish-to-start link is primarily created when you link two tasks using the Link Tasks feature on the Task tab.