Sportly, Inc. completed Job No. B14 during 2011. The job cost sheet listed the following: Direct materials $44,000 Direct labor $24,000 Manufacturing overhead applied $16,000 Units produced 3,000 units Units sold 1,800 units How much is the cost of the finished goods on hand from this job

Sagot :

Based on the direct materials, the direct labor, and the manufacturing overhead, the cost of finished goods on hand is $33,600.

What is the cost of finished goods on hand for this job?

Cost of goods on hand is:

= Cost of goods per unit x Number of goods on hand

Cost of goods per unit is:
= (44,000 + 24,000 + 16,000) / 3,000 units

= $28 per unit

Cost of goods on hand:

= 28 x (3,000 - 1,800)

= $33,600

Find out more on finished goods at https://brainly.com/question/26764271.

#SPJ1

Your engagement is important to us. Keep sharing your knowledge and experiences. Let's create a learning environment that is both enjoyable and beneficial. IDNLearn.com is dedicated to providing accurate answers. Thank you for visiting, and see you next time for more solutions.